Control Account

A formal control point in the project where scope, budget, actual costs, and schedule are brought together and evaluated against earned value to measure performance.

Key Points

  • Located at the intersection of a WBS element and the responsible organization (OBS), typically managed by a Control Account Manager (CAM).
  • Groups related work into work packages and, when needed, planning packages under a single performance baseline.
  • Serves as the unit for earned value calculations and variance analysis (PV, EV, AC, SV, CV).
  • Enables consistent performance tracking and roll-up reporting to higher project levels.

Example

In a hospital IT upgrade, the "Network Infrastructure" control account aligns WBS 2.3 with the Network Team. It has a time-phased budget of $600,000. After two months, PV = $200,000, EV = $180,000, and AC = $220,000. The CAM notes both a cost overrun and schedule slippage and proposes corrective actions such as resource reallocation and supplier negotiation.

PMP Example Question

Where are scope, budget, schedule, and actual cost integrated and compared to earned value to assess performance?

  1. Work package
  2. Control account
  3. Project charter
  4. Cost center

Correct Answer: B — Control account

Explanation: A control account is the defined point in the WBS-OBS structure where performance is measured using earned value metrics.

AI-Prompt Engineering for Strategic Leaders

Stop managing administration and start leading the future. This course is built specifically for managers and project professionals who want to automate chaos and drive strategic value using the power of artificial intelligence.

We don't teach you how to program Python; we teach you how to program productivity. You will master the AI-First Mindset and the 'AI Assistant' model to hand off repetitive work like status reports and meeting minutes so you can focus on what humans do best: empathy, negotiation, and vision.

Learn the 5 Core Prompt Elements-Role, Goal, Context, Constraints, and Output-to get high-quality results every time. You will build chained sequences for complex tasks like auditing schedules or simulating risks, while navigating ethics and privacy with human-in-the-loop safeguards.

Move from being an administrative manager to a high-value strategic leader. Future-proof your career today with practical, management-focused AI workflows that map to your real-world challenges. Enroll now and master the language of the future.

Explore the Course


Take Control of Project Performance!

HK School of Management and Technology helps you go beyond status reports and gut feelings. In this advanced course, you will learn Earned Value Management (EVM) to measure progress, forecast outcomes, and take corrective action. Learn how WBS quality drives performance, how control accounts work, and how to use EAC, TCPI, and variance analysis. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More