Contingency

A possible event or situation that might influence how the project is carried out and is anticipated by setting aside time, cost, or resource reserves.

Key Points

  • Represents potential events (known-unknown risks) that could affect scope, schedule, cost, or quality.
  • Handled through contingency reserves that are included in the approved baseline.
  • Should be tied to specific risk responses and activation triggers.
  • Different from management reserve, which covers unknown-unknowns outside the baseline.

Example

A software project anticipates possible integration issues with a third-party API. The team sets a 10% schedule buffer and a $25,000 contingency to fund extra testing and bug fixes if the integration fails initial tests. If the first integration test has critical defects (trigger), the contingency is drawn down.

PMP Example Question

Which statement best describes a contingency in project risk management?

  1. A possible event that may affect the project and is planned for by allocating reserves.
  2. Budget held by senior management for unforeseen work outside the baseline.
  3. Extra time added by team members to make estimates feel safe.
  4. A mandatory change request raised whenever a risk occurs.

Correct Answer: A — A possible event planned for with reserves

Explanation: A contingency is a potential event that could impact the project and is addressed by including contingency reserves in the baseline. Option B describes management reserve, C is padding, and D is a process action, not the definition.

ICS/OT Incident Response Drills and Exercises

An incident response plan is only a theory until the people who must use it have run it under pressure. This course helps OT engineers, operations leaders, IT responders, and security teams turn a plan on paper into a tested capability.

Define safe states and manual fallback before an incident forces the decision. Build escalation paths, tabletop exercises, and scenarios that expose the gaps a document review cannot find.

Then turn the results into evidence: an after-action report, owned improvements, recovery checks, and a drill cadence that keeps the program alive after the exercise ends.

24 lessons, 2.4 hours. US$47 one-time through HKSM Courses. 30-day money-back guarantee when 50% or less consumed.

Explore the Course


ICS/OT Incident Response Drills and Exercises course preview

Launch your career!

HK School of Management and Technology provides world-class training in Project Management with AI and Agile Methodologies. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More