Claims Administration

The organized handling of contract claims, including their intake, evaluation and decision, and formal notification of the results to the involved parties.

Key Points

  • Manages formal requests for adjustment under a contract when the buyer and seller disagree.
  • Typical steps: receive and log the claim, assess it against contract terms and evidence, issue a decision, and communicate outcomes within required timeframes.
  • Relies on strong documentation and traceability for audits and potential negotiation, mediation, arbitration, or litigation.
  • Results may include approved change orders or equitable adjustments, denial of the claim, and updates to project records and baselines.

Example

A contractor files a claim for extra payment due to differing site conditions. The project team records the claim, reviews contract clauses on site conditions, analyzes cost and schedule impacts, renders a written decision, and formally communicates the outcome to the contractor, with next steps and timelines for appeal.

PMP Example Question

During execution, a seller submits a formal request for additional payment due to scope ambiguity. You log the request, evaluate it against contract terms, issue a decision, and notify the seller in writing. What process are you performing?

  1. Claims administration
  2. Contract change control
  3. Conduct Procurements
  4. Procurement performance review

Correct Answer: A — Claims administration

Explanation: Claims administration is the process of receiving, deciding on, and formally communicating outcomes for contract claims.

Leadership for Project Managers Course

Lead with clarity, confidence, and real impact. This Leadership for Project Managers course turns day-to-day challenges—unclear priorities, tough stakeholders, and cross-functional friction—into opportunities to guide teams and deliver outcomes that matter.

You’ll learn practical leadership skills tailored to project realities: setting direction without overcontrol, creating alignment across functions, and building commitment even when authority is limited. We go beyond theory with tools you can use immediately—one-sentence visioning, stakeholder influence maps, decision framing, and feedback scripts that actually land.

Expect hands-on frameworks, real-world examples, and guided practice to prepare for tough moments—executive readouts, resistance from stakeholders, and high-stakes negotiations. Downloadable templates and checklists keep everything actionable when the pace gets intense.

Learn alongside professionals around the world working in project leadership and delivery.

Explore the Course


Build an ICS/OT cybersecurity foundation that fits the real environment

Standard IT controls can disrupt the industrial systems they are meant to protect. Learn how to assess OT risk, design zones and conduits, apply IEC 62443 security levels, use MITRE ATT&CK for ICS, and establish passive asset visibility without risking production. Eight reconstructed incidents connect attacker techniques to the controls that failed, giving you the vocabulary and judgment to make credible security decisions from day one.

Explore the Course