Change Request

An official, documented request to alter a project document, a deliverable, or an approved baseline.

Key Points

  • Must be documented and submitted for review through the change control process.
  • May propose corrective or preventive actions, defect repairs, or updates to project documents.
  • Changes to a baseline require approval before implementation.
  • Should include impact analysis on scope, schedule, cost, quality, and risk.

Example

After scope is baselined, a client asks for an extra reporting feature. The project manager prepares a change request detailing impacts on schedule and cost and submits it to the change control board for a decision before any work begins.

PMP Example Question

A stakeholder asks to add functionality after the scope baseline is approved. What should the project manager do next?

  1. Implement the change if it increases business value.
  2. Have the team estimate and start the work immediately.
  3. Submit a formal change request for evaluation through change control.
  4. Update the risk register and proceed with the change.

Correct Answer: C — Submit a formal change request

Explanation: Once baselines are approved, any modification must go through the formal change control process and be approved before implementation.

Leadership for Project Managers Course

Lead with clarity, confidence, and real impact. This Leadership for Project Managers course turns day-to-day challenges—unclear priorities, tough stakeholders, and cross-functional friction—into opportunities to guide teams and deliver outcomes that matter.

You’ll learn practical leadership skills tailored to project realities: setting direction without overcontrol, creating alignment across functions, and building commitment even when authority is limited. We go beyond theory with tools you can use immediately—one-sentence visioning, stakeholder influence maps, decision framing, and feedback scripts that actually land.

Expect hands-on frameworks, real-world examples, and guided practice to prepare for tough moments—executive readouts, resistance from stakeholders, and high-stakes negotiations. Downloadable templates and checklists keep everything actionable when the pace gets intense.

Ready to influence without waiting for a bigger title? Join a community of ambitious PMs, sharpen your edge, and deliver with purpose—project after project.



Advance your Lean Six Sigma expertise!

HK School of Management helps you take Lean Six Sigma to the next level—without the overwhelm. Master advanced statistical tools, Excel-based analysis, and real-world improvement techniques to solve complex problems with confidence. For the price of lunch, you get practical templates, guided examples, and hands-on project experience you can use immediately at work. Backed by our 30-day money-back guarantee—zero risk, real impact.

Learn More