Change Management Plan

A section of the project management plan that sets up the change control board, defines the scope of its decision-making authority, and explains how the change control system will be carried out.

Key Points

  • Establishes the change control board (CCB), its membership, roles, and decision rules.
  • Defines how change requests are submitted, analyzed, approved or rejected, and recorded.
  • Specifies authority limits, escalation thresholds, response timelines, and communication steps.
  • Describes tools, artifacts, and interfaces with the change log and configuration management.

Example

On a hospital IT upgrade, the plan names the CIO, project manager, and clinical lead as the CCB, sets a 5-business-day decision SLA, requires impact analysis on scope, schedule, cost, quality, and risk, and mandates that approved changes are baselined and communicated via a weekly change bulletin.

PMP Example Question

Which document defines who sits on the change control board, how much authority they have, and the steps for evaluating and implementing change requests?

  1. Issue Log
  2. Change Log
  3. Configuration Management Plan
  4. Change Management Plan

Correct Answer: D — Change Management Plan

Explanation: The change management plan establishes the CCB, its authority, and the procedures for processing and implementing changes.

Leadership for Project Managers Course

Lead with clarity, confidence, and real impact. This Leadership for Project Managers course turns day-to-day challenges—unclear priorities, tough stakeholders, and cross-functional friction—into opportunities to guide teams and deliver outcomes that matter.

You’ll learn practical leadership skills tailored to project realities: setting direction without overcontrol, creating alignment across functions, and building commitment even when authority is limited. We go beyond theory with tools you can use immediately—one-sentence visioning, stakeholder influence maps, decision framing, and feedback scripts that actually land.

Expect hands-on frameworks, real-world examples, and guided practice to prepare for tough moments—executive readouts, resistance from stakeholders, and high-stakes negotiations. Downloadable templates and checklists keep everything actionable when the pace gets intense.

Ready to influence without waiting for a bigger title? Join a community of ambitious PMs, sharpen your edge, and deliver with purpose—project after project.



Take Control of Project Performance!

HK School of Management helps you go beyond status reports and gut feelings. In this advanced course, you’ll master Earned Value Management (EVM) to objectively measure progress, forecast outcomes, and take corrective action with confidence. Learn how WBS quality drives performance, how control accounts really work, and how to use EAC, TCPI, and variance analysis to make smarter decisions—before projects drift off track. Built around real-world examples and hands-on exercises, this course gives you practical tools you can apply immediately. Backed by our 30-day money-back guarantee—low risk, high impact for serious project professionals.

Learn More