Change

An alteration made to any baselined deliverable, a component of the project management plan, or a project document that is under formal control.

Key Points

  • Applies only to items under formal configuration or baseline control.
  • Documented through a change request and analyzed for impact on scope, schedule, cost, quality, and risk.
  • Requires approval through the defined change control process (e.g., CCB) before implementation.
  • Once approved, triggers updates to baselines, plans, and related documents, and must be communicated to stakeholders.

Example

A sponsor asks to add a new compliance report after the scope baseline is approved. The project manager logs a change request, performs impact analysis on cost and schedule, seeks CCB approval, and if approved, updates the scope baseline, schedule, and reporting deliverables.

PMP Example Question

Which statement best describes a change in a formally controlled project environment?

  1. An informal suggestion shared during a team stand-up.
  2. A variance noted in a status report that requires no follow-up.
  3. Any proposed or approved alteration to a baselined deliverable, plan component, or controlled project document.
  4. A quick fix implemented by the technical lead to satisfy a user request.

Correct Answer: C — An alteration to a baselined deliverable, plan component, or controlled project document

Explanation: A change affects items under formal control and must follow the change control process, including documentation, impact analysis, and approval.

AI for Project Managers — Build Plans Faster, Lead Better

Turn messy inputs into structured project plans in minutes. If you are a project manager tired of spending hours on documentation, this course shows you how to use AI to work faster while staying fully in control.

This is not a generic AI course. You will learn how to use AI as a practical co-pilot to build real project artifacts—charters, WBS, schedules, risk registers, and executive reports—using structured, reliable prompt frameworks.

You will also learn how to keep your project aligned across scope, schedule, cost, and risk, and how to interpret performance data like Earned Value Management to support better decisions and communication.

Everything is designed for immediate use. You get ready-to-use prompt templates and workflows you can apply right away in your projects. Watch the video to see how it works and start building your first AI-supported project plan.

Explore the Course


Lead with clarity, influence, and outcomes.

HK School of Management and Technology offers a practical Leadership for Project Managers course for real projects, tight deadlines, and cross-functional teams. Learn to set direction, align stakeholders, and drive commitment without relying on title. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More