Bottom-Up Estimating

An estimating approach that calculates total project cost or duration by first estimating each detailed WBS work package and then summing those estimates to the higher levels.

Key Points

  • Starts at the lowest-level WBS components and rolls estimates up to summary levels.
  • Typically more accurate than top-down methods, but requires more time and effort.
  • Relies on a complete WBS and input from subject matter experts for each work package.
  • Creates traceable, documented estimates and a defensible basis of estimate.

Example

A project manager for an ERP rollout asks functional leads to estimate hours and costs for each WBS work package: data migration, interface development, testing, training, and deployment. After gathering these detailed estimates, the PM aggregates them to produce the overall project duration and budget.

PMP Example Question

Your team has finalized the WBS. You ask each work package owner to estimate effort and cost for their activities and then sum these values to determine the project totals. Which technique are you using?

  1. Bottom-up estimating
  2. Analogous estimating
  3. Parametric estimating
  4. Three-point estimating

Correct Answer: A — estimating by rolling up work package estimates

Explanation: Bottom-up estimating aggregates detailed WBS work package estimates. Analogous is top-down using historical data, parametric uses unit rates, and three-point applies uncertainty ranges to individual estimates.

AI for Project Managers — Build Plans Faster, Lead Better

Turn messy inputs into structured project plans in minutes. If you are a project manager tired of spending hours on documentation, this course shows you how to use AI to work faster while staying fully in control.

This is not a generic AI course. You will learn how to use AI as a practical co-pilot to build real project artifacts—charters, WBS, schedules, risk registers, and executive reports—using structured, reliable prompt frameworks.

You will also learn how to keep your project aligned across scope, schedule, cost, and risk, and how to interpret performance data like Earned Value Management to support better decisions and communication.

Everything is designed for immediate use. You get ready-to-use prompt templates and workflows you can apply right away in your projects. Watch the video to see how it works and start building your first AI-supported project plan.



Launch your Agile career!

HK School of Management helps you master Agile and Scrum—faster. Learn practical playbooks, AI-powered prompts, and real-world workflows to plan smarter, deliver sooner, and keep stakeholders aligned. For the price of lunch, you’ll get templates, tools, and step-by-step guidance to level up your projects. Backed by our 30-day money-back guarantee—zero risk, clear path to results.

Learn More