Backward Pass

A CPM technique that figures out each activity's late start and late finish by moving backward through the schedule from the project's completion date.

Key Points

  • Part of the critical path method, performed after or alongside the forward pass.
  • Starts at the project finish (or latest imposed finish) and works backward through the network.
  • For each activity: late finish (LF) is typically the minimum late start (LS) of its successors; late start (LS) = LF - duration, adjusted for leads/lags and relationship types.
  • Provides late dates used to compute float and confirm the critical path (zero total float).

Example

You have a project that must finish on day 50. Activity D (3 days) feeds two successors: E and F. From earlier calculations, LS(E) = day 30 and LS(F) = day 32. In the backward pass, D's LF = min(30, 32) = 30, and D's LS = 30 - 3 = day 27. Repeat this for all predecessors, moving backward until you reach the project's start.

PMP Example Question

Which scheduling step uses the project finish date to determine activities' late start and late finish dates?

  1. Forward pass
  2. Backward pass
  3. Resource leveling
  4. Rolling wave planning

Correct Answer: B — Backward pass

Explanation: The backward pass starts from the project completion date and calculates late dates for each activity, enabling float and critical path determination.

Advanced Project Management — Measuring Project Performance

Move beyond guesswork and status reporting. This course helps you measure real progress, spot problems early, and make confident decisions using proven project performance techniques. If you manage complex projects and want clearer visibility and control, this course is built for you.

This is not abstract theory. You’ll work step by step through Earned Value Management (EVM), learning how cost, schedule, and scope come together to show true performance. You’ll build a solid foundation in EVM concepts, understand why formulas work, and learn how performance data actually supports leadership decisions.

You’ll master Work Breakdown Structures (WBS), control accounts, and budget baselines, then apply core EVM metrics like EAC, TCPI, and variance analysis. Through a detailed real-world example, you’ll forecast outcomes, analyze trends, and understand contingencies and management reserves with confidence.

Learn how experienced project managers monitor performance, communicate results clearly, and take corrective action before projects slip. With practical exercises and hands-on analysis, you’ll be ready to apply EVM immediately. Enroll now and start managing performance with clarity and control.

Explore the Course


Run the drill before the incident runs you

Design, run and prove OT drills and tabletop exercises before an incident tests your team. OT Incident Drills and Exercises includes 24 lessons and practical exercise materials, delivered through HKSM Courses for US$47 one-time. 30-day money-back guarantee when 50% or less of the course has been consumed.

Explore the Course