Backward Pass

A CPM technique that figures out each activity's late start and late finish by moving backward through the schedule from the project's completion date.

Key Points

  • Part of the critical path method, performed after or alongside the forward pass.
  • Starts at the project finish (or latest imposed finish) and works backward through the network.
  • For each activity: late finish (LF) is typically the minimum late start (LS) of its successors; late start (LS) = LF - duration, adjusted for leads/lags and relationship types.
  • Provides late dates used to compute float and confirm the critical path (zero total float).

Example

You have a project that must finish on day 50. Activity D (3 days) feeds two successors: E and F. From earlier calculations, LS(E) = day 30 and LS(F) = day 32. In the backward pass, D's LF = min(30, 32) = 30, and D's LS = 30 - 3 = day 27. Repeat this for all predecessors, moving backward until you reach the project's start.

PMP Example Question

Which scheduling step uses the project finish date to determine activities' late start and late finish dates?

  1. Forward pass
  2. Backward pass
  3. Resource leveling
  4. Rolling wave planning

Correct Answer: B — Backward pass

Explanation: The backward pass starts from the project completion date and calculates late dates for each activity, enabling float and critical path determination.

AI-Prompt Engineering for Strategic Leaders

Stop managing administration and start leading the future. This course is built specifically for managers and project professionals who want to automate chaos and drive strategic value using the power of artificial intelligence.

We don't teach you how to program Python; we teach you how to program productivity. You will master the AI-First Mindset and the 'AI Assistant' model to hand off repetitive work like status reports and meeting minutes so you can focus on what humans do best: empathy, negotiation, and vision.

Learn the 5 Core Prompt Elements-Role, Goal, Context, Constraints, and Output-to get high-quality results every time. You will build chained sequences for complex tasks like auditing schedules or simulating risks, while navigating ethics and privacy with human-in-the-loop safeguards.

Move from being an administrative manager to a high-value strategic leader. Future-proof your career today with practical, management-focused AI workflows that map to your real-world challenges. Enroll now and master the language of the future.



Launch your Agile career!

HK School of Management helps you master Agile and Scrum—faster. Learn practical playbooks, AI-powered prompts, and real-world workflows to plan smarter, deliver sooner, and keep stakeholders aligned. For the price of lunch, you’ll get templates, tools, and step-by-step guidance to level up your projects. Backed by our 30-day money-back guarantee—zero risk, clear path to results.

Learn More