Analogous Estimating

A method that estimates an activity's or a project's time or cost by drawing on data from comparable past work.

Key Points

  • Top-down approach used when limited detail is available.
  • Relies on historical results from similar projects and expert judgment.
  • Requires adjustments for differences in size, complexity, scope, or location.
  • Faster but typically less accurate than bottom-up or parametric estimating.

Example

A team delivered a data center upgrade last year in 8 months for USD 900,000. A new upgrade has a similar scope but slightly higher capacity. Using analogous estimating, the project manager uses last year's figures and applies a 10 percent uplift, forecasting about 8.8 months and USD 990,000 as a high-level estimate.

PMP Example Question

During project initiation, the sponsor requests a quick, high-level cost figure before detailed planning begins. Which estimating technique should the project manager use?

  1. Bottom-up estimating
  2. Analogous estimating
  3. Three-point estimating
  4. Parametric estimating

Correct Answer: B - Analogous estimating

Explanation: Analogous estimating provides a rapid, top-down estimate using data from similar past projects, making it suitable early in the project when detail is limited.

AI Systems with Claude, for Scrum Masters and Project Managers

Most AI pilots in project management do not fail on the model. They fail because somebody pointed the thing at a decision instead of at a task. This course is built around that distinction, and around the work that follows once you get it right.

Eight teaching sections, taught against one running project from the first lecture to the last. You watch a system get built, then you build the same one against your own sprint. Nothing here is a demo that works only on the example.

You finish with five working systems and you keep them. The sprint report machine turns your board export and standup notes into the report you currently write by hand. The retro intelligence system tells you what the team keeps saying, not just what it said this time. The stakeholder comms engine drafts the update in the register the audience expects. The backlog health monitor flags the quiet decay nobody has time to check for. The risk and dependency tracker follows the chains that actually bite.

Seventy-six working files ship with it, across four sections, so every system is built against real sprint data rather than material invented for a slide. Four sprints of retrospectives, board exports, standup notes, backlog and risk data.

Explore the Course


Become an AI-First Agile Leader!

HK School of Management and Technology helps you apply AI to Agile work with practical, prompt-based workflows for real-world Scrum challenges. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More