Actual Duration

The elapsed calendar time from the moment an activity actually starts to the project’s data (status) date if it is still underway, or to its actual finish date if it has been completed.

Key Points

  • Measured in calendar units (e.g., days or weeks), not effort hours.
  • Begins at the activity’s actual start; ends at the data date if in progress or at the actual finish if complete.
  • Grows with each status update until the activity is finished.
  • Compared with planned and remaining duration to evaluate schedule performance.

Example

An activity begins on January 5 and finishes on January 14. The Actual Duration is 10 calendar days (Jan 5–Jan 14). If on January 12 the activity were still in progress and the project’s data date were January 12, the Actual Duration at that time would be the calendar time from Jan 5 to Jan 12.

PMP Example Question

Which statement best describes Actual Duration for a schedule activity?

  1. The time scheduled between the planned start and planned finish dates.
  2. The calendar time from the actual start to the data date if in progress, or to the actual finish if complete.
  3. The total labor hours expended by team members on the activity.
  4. The forecasted time needed to complete the remaining work.

Correct Answer: B — Calendar time from actual start to the data date or actual finish

Explanation: Actual Duration measures elapsed calendar time based on what has actually occurred, not planned dates, effort hours, or forecasts.

ICS/OT Cybersecurity Fundamentals — Security Built for Industrial Systems

Industrial control systems cannot be secured like ordinary IT. A forced reboot, aggressive scan, or incompatible patch can interrupt production and create real safety consequences. Effective OT security begins with understanding the systems, constraints, and risks unique to industrial environments.

This course gives IT professionals, engineers, operators, and security practitioners a practical foundation in ICS threats, zone and conduit design, risk assessment, passive asset visibility, and vendor evaluation. You will learn how IEC 62443, NIST CSF, and MITRE ATT&CK for ICS apply where availability and safety come first.

Eight reconstructed incidents—including Stuxnet, Triton, Ukraine 2015, Colonial Pipeline, and PIPEDREAM—show how attackers move through OT environments, what they target, and which defenses could have changed the outcome.

Watch the course preview, then build the vocabulary, frameworks, and judgment needed to take credible first steps in ICS/OT cybersecurity.

Explore the Course


ICS/OT Cybersecurity Fundamentals course preview

Build complete project plans in minutes with AI

Learn how to use AI to create charters, WBSs, schedules, risk registers, and executive reports while staying in control. This course gives you prompt templates and practical workflows based on real project work. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More