Activity List

A recorded inventory of all scheduled activities that includes each activity’s description, a unique identifier, and enough detail about the work so the team clearly understands what needs to be done.

Key Points

  • Lists every scheduled activity with a unique ID and clear description.
  • Includes sufficient scope detail so team members know the exact work required.
  • Serves as a basis for sequencing, estimating durations and costs, and building the schedule.
  • Is maintained and updated as scope and planning information evolve.

Example

In a website redesign project, the Activity List might include: A101 — Gather requirements (interview stakeholders, collect current analytics); A120 — Create wireframes (home, product, checkout pages); A140 — Develop front-end (HTML/CSS/JS for approved designs). Each item has an ID, description, and details so the assigned team knows exactly what to deliver.

PMP Example Question

Which project document specifically contains the activity description, activity identifier, and detailed work information needed so team members know what to perform?

  1. Activity List
  2. Work Breakdown Structure (WBS)
  3. Project Network Diagram
  4. Milestone List

Correct Answer: A — Activity List

Explanation: The Activity List records each scheduled activity with its unique ID and detailed description, ensuring clarity of the work to be performed; the WBS decomposes scope, the network diagram shows sequencing, and the milestone list tracks significant points without detailed work descriptions.

Advanced Project Management — Measuring Project Performance

Move beyond guesswork and status reporting. This course helps you measure real progress, spot problems early, and make confident decisions using proven project performance techniques. If you manage complex projects and want clearer visibility and control, this course is built for you.

This is not abstract theory. You’ll work step by step through Earned Value Management (EVM), learning how cost, schedule, and scope come together to show true performance. You’ll build a solid foundation in EVM concepts, understand why formulas work, and learn how performance data actually supports leadership decisions.

You’ll master Work Breakdown Structures (WBS), control accounts, and budget baselines, then apply core EVM metrics like EAC, TCPI, and variance analysis. Through a detailed real-world example, you’ll forecast outcomes, analyze trends, and understand contingencies and management reserves with confidence.

Learn how experienced project managers monitor performance, communicate results clearly, and take corrective action before projects slip. With practical exercises and hands-on analysis, you’ll be ready to apply EVM immediately. Enroll now and start managing performance with clarity and control.



Take Control of Project Performance!

HK School of Management helps you go beyond status reports and gut feelings. In this advanced course, you’ll master Earned Value Management (EVM) to objectively measure progress, forecast outcomes, and take corrective action with confidence. Learn how WBS quality drives performance, how control accounts really work, and how to use EAC, TCPI, and variance analysis to make smarter decisions—before projects drift off track. Built around real-world examples and hands-on exercises, this course gives you practical tools you can apply immediately. Backed by our 30-day money-back guarantee—low risk, high impact for serious project professionals.

Learn More