Activity Attributes

A set of descriptive details captured for every scheduled activity in the activity list. These details may include items like activity identifiers or codes; predecessors and successors; the type of dependency between activities; any leads or lags; resource needs; target or imposed dates; constraints; and key assumptions.

Key Points

  • They are metadata about an activity that help define, organize, and control the schedule.
  • Typical items include activity codes, predecessors, successors, relationship types, leads/lags, resource requirements, imposed dates, constraints, and assumptions.
  • They support sequencing, estimating durations and costs, resource planning, and schedule analysis (e.g., critical path and network logic).
  • Attributes can be refined over time as more information becomes available, enabling better filtering, grouping, and reporting.

Example

For activity A-104 “Install Server OS”: activity code A-104; predecessor A-103 “Rack Servers” with a finish-to-start relationship and a 2‑day lag; successor A-105 “Configure Network”; resources: 1 systems engineer and 1 technician; imposed date: start no earlier than May 10; constraint: hardware must pass burn-in; assumption: network VLANs will be available by May 9.

PMP Example Question

Which project document records details such as an activity’s predecessors and successors, dependency type, leads and lags, resource needs, imposed dates, constraints, and assumptions?

  1. Activity List
  2. Activity Attributes
  3. WBS Dictionary
  4. Milestone List

Correct Answer: B — Activity Attributes

Explanation: Activity attributes capture descriptive data for each activity, including codes, logical relationships, leads/lags, resource requirements, imposed dates, constraints, and assumptions.

Advanced Lean Six Sigma — Data-Driven Excellence

Solve complex problems, reduce variation, and improve performance with confidence. This course is designed for professionals who already know the basics and want to apply advanced Lean Six Sigma tools to real business challenges.

This is not abstract statistics or theory-heavy training. You’ll use Excel to perform real analysis, interpret results correctly, and apply tools like DMAIC, SIPOC, MSA, hypothesis testing, and regression without memorizing formulas or relying on expensive software.

You’ll learn how to measure baseline performance, analyze process capability, use control charts to maintain stability, and validate improvements using statistical evidence. Templates, worked examples, and structured walkthroughs help you apply each concept immediately.

Learn through a complete, real-world Lean Six Sigma project and develop the skills to lead data-driven improvements with credibility. If you’re ready to move beyond basics and make decisions backed by data, enroll now and take your Lean Six Sigma expertise to the next level.

Explore the Course


Launch your Agile career!

HK School of Management and Technology helps you learn Agile and Scrum with practical playbooks, AI-powered prompts, and real-world workflows for planning and delivery. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More