Acquisition

Securing the people, equipment, and other tangible resources needed to carry out project work. Obtaining these resources involves a cost to gain access, which may be monetary or take non-cash forms such as internal chargebacks, opportunity cost, or time commitments.

Key Points

  • Includes both human resources (staff, contractors) and physical resources (tools, facilities, materials).
  • Resources can come from internal departments or external suppliers, often requiring procurement or staffing actions.
  • Costs are not limited to payments; they can include internal allocations, opportunity costs, or schedule impacts.
  • Planned through resource and procurement processes; lead times and availability influence schedule and risk.

Example

On a construction project, the project manager rents a crane for two weeks and contracts a certified operator. The rental is a cash expense, while reassigning an in-house rigger from operations represents a non-cash opportunity cost due to reduced operational capacity.

PMP Example Question

Which activity best illustrates acquisition in a project context?

  1. Negotiating with a staffing vendor to bring in two developers for three months.
  2. Re-sequencing tasks to smooth out over-allocated resources.
  3. Updating the risk register after discovering a skills gap.
  4. Calculating cost performance index during monthly reporting.

Correct Answer: A — Securing needed people from an external source

Explanation: Acquisition is about obtaining human and material resources to do the work. Negotiating with a vendor to obtain developers is acquisition; the other options relate to resource optimization, risk management, or performance measurement.

Advanced Project Management — Measuring Project Performance

Move beyond guesswork and status reporting. This course helps you measure real progress, spot problems early, and make confident decisions using proven project performance techniques. If you manage complex projects and want clearer visibility and control, this course is built for you.

This is not abstract theory. You’ll work step by step through Earned Value Management (EVM), learning how cost, schedule, and scope come together to show true performance. You’ll build a solid foundation in EVM concepts, understand why formulas work, and learn how performance data actually supports leadership decisions.

You’ll master Work Breakdown Structures (WBS), control accounts, and budget baselines, then apply core EVM metrics like EAC, TCPI, and variance analysis. Through a detailed real-world example, you’ll forecast outcomes, analyze trends, and understand contingencies and management reserves with confidence.

Learn how experienced project managers monitor performance, communicate results clearly, and take corrective action before projects slip. With practical exercises and hands-on analysis, you’ll be ready to apply EVM immediately. Enroll now and start managing performance with clarity and control.



Take Control of Project Performance!

HK School of Management helps you go beyond status reports and gut feelings. In this advanced course, you’ll master Earned Value Management (EVM) to objectively measure progress, forecast outcomes, and take corrective action with confidence. Learn how WBS quality drives performance, how control accounts really work, and how to use EAC, TCPI, and variance analysis to make smarter decisions—before projects drift off track. Built around real-world examples and hands-on exercises, this course gives you practical tools you can apply immediately. Backed by our 30-day money-back guarantee—low risk, high impact for serious project professionals.

Learn More