7.4 Control Scope

7.4 Control Scope
Inputs Tools & Techniques Outputs

Replace this with term.

Purpose & When to Use

Control Scope keeps the project focused on the agreed deliverables. It verifies what is completed against the scope baseline and manages any requested changes through a formal process. Use it throughout the project once the scope baseline is set, and apply it regularly in both predictive and adaptive life cycles.

Mini Flow (How It’s Done)

  • Review the scope baseline: scope statement, WBS, and WBS dictionary.
  • Collect actuals: completed work, deliverable status, and requirement fulfillment from the requirements traceability matrix.
  • Compare actuals to the baseline and analyze variances and trends.
  • Identify unapproved additions (scope creep) and stop them from proceeding.
  • Evaluate needed changes; submit formal change requests with impact analysis on schedule, cost, quality, risks, and benefits.
  • Process changes through integrated change control; implement only approved changes.
  • Update the scope baseline, WBS, RTM, and related plans and documents after approval.
  • Communicate status, variances, and decisions to stakeholders; adjust backlog or release plan in adaptive approaches.

Quality & Acceptance Checklist

  • Scope baseline is current, version-controlled, and accessible.
  • Each deliverable has clear, measurable acceptance criteria.
  • All scope changes are submitted, reviewed, and approved or rejected formally.
  • Requirements traceability matrix shows status, tests, and acceptance for each requirement.
  • Approved changes are reflected in the WBS, schedule, budget, and risks.
  • Variance analysis (e.g., scope performance, trend) is documented with actions.
  • Instances of gold plating or scope creep are recorded and corrected.
  • Stakeholder communications and acceptance records are complete and archived.

Common Mistakes & Exam Traps

  • Confusing Control Scope (monitor and manage changes) with Validate Scope (formal acceptance of completed deliverables).
  • Allowing team or stakeholders to add features without approval (gold plating or scope creep).
  • Updating schedule or cost without updating the scope baseline and WBS after a change is approved.
  • Skipping impact analysis before submitting or deciding on a change request.
  • Not using the requirements traceability matrix to verify each requirement’s status and tests.
  • Treating defect repair as a scope change without checking if it restores the baseline deliverable.
  • Assuming internal completion equals acceptance; acceptance must match stated criteria.

PMP Example Question

A stakeholder asks the team to add a minor feature. The team has started work on it to save time. What should the project manager do next?

  1. Allow the team to finish since the change is small and will delight the customer.
  2. Submit a formal change request and assess impacts before any additional work continues.
  3. Update the WBS and schedule to include the extra work and inform stakeholders.
  4. Reject the change immediately and forbid any future change requests.

Correct Answer: B — Submit a formal change request and assess impacts before any additional work continues.

Explanation: Only approved changes should be implemented. Control Scope prevents scope creep and ensures changes go through formal change control with impact analysis.

Agile Project Management & Scrum — With AI

Ship value sooner, cut busywork, and lead with confidence. Whether you’re new to Agile or scaling multiple teams, this course gives you a practical system to plan smarter, execute faster, and keep stakeholders aligned.

This isn’t theory—it’s a hands-on playbook for modern delivery. You’ll master Scrum roles, events, and artifacts; turn vision into a living roadmap; and use AI to refine backlogs, write clear user stories and acceptance criteria, forecast with velocity, and automate status updates and reports.

You’ll learn estimation, capacity and release planning, quality and risk management (including risk burndown), and Agile-friendly EVM—plus how to scale with Scrum of Scrums, LeSS, SAFe, and more. Downloadable templates and ready-to-use GPT prompts help you apply everything immediately.

Learn proven patterns from real projects and adopt workflows that reduce meetings, improve visibility, and boost throughput. Ready to level up your delivery and lead in the AI era? Enroll now and start building smarter sprints.



Take Control of Project Performance!

HK School of Management helps you go beyond status reports and gut feelings. In this advanced course, you’ll master Earned Value Management (EVM) to objectively measure progress, forecast outcomes, and take corrective action with confidence. Learn how WBS quality drives performance, how control accounts really work, and how to use EAC, TCPI, and variance analysis to make smarter decisions—before projects drift off track. Built around real-world examples and hands-on exercises, this course gives you practical tools you can apply immediately. Backed by our 30-day money-back guarantee—low risk, high impact for serious project professionals.

Learn More