Stakeholders
Stakeholders are individuals, groups, or organizations that can affect, be affected by, or perceive themselves to be affected by a project or its outcomes.
Why this domain matters
Projects exist in a network of people with different interests, power levels, and expectations. Effective stakeholder engagement helps align expectations, secure support, and reduce resistance. Ignoring key stakeholders leads to hidden opposition, late surprises, and outcomes that may be technically correct but practically unusable.
Key concepts
- Stakeholder identification: systematically finding all relevant stakeholders early and throughout the project.
- Stakeholder analysis: understanding influence, interest, expectations, and possible impact on the project.
- Stakeholder engagement plan: strategies for communication, involvement, and managing expectations.
- Communication channels: formal and informal methods to share information and gather feedback.
- Ongoing engagement: monitoring sentiment and adjusting strategies as the project and context change.
Common pitfalls and exam traps
- Treating stakeholder engagement as a one-time list instead of an ongoing process.
- Focusing only on supportive stakeholders and ignoring opponents or skeptics.
- Assuming the sponsor speaks for all stakeholders and skipping broader engagement.
- Using a single communication style for everyone, regardless of their needs and influence.
- Exam trap: jumping to “send a status report” when the better answer is to analyze or re-engage stakeholders strategically.
PMP Example Question
PMP Example Question
A new senior executive joins the organization and is identified as a high-influence stakeholder. They have strong concerns about the project’s approach and are not convinced of its benefits. What should the project manager do first?
- Escalate the issue to the sponsor and ask them to handle the situation.
- Send the executive the latest status report and project charter.
- Meet with the executive to understand their concerns and expectations.
- Ignore the concern because the project has already been approved.
Correct Answer: C — Meet with the executive to understand their concerns and expectations.
Explanation: When a new, powerful stakeholder appears with concerns, the project manager should first seek to understand their perspective through direct engagement. This information then feeds into updated stakeholder analysis and engagement plans. Automatically escalating, sending generic documents, or ignoring the stakeholder does not address the underlying concerns.