To-complete performance index

A forward-looking cost efficiency metric that indicates the performance needed on the remaining work to meet a selected cost target (BAC or EAC). It helps determine achievability and guides corrective actions during cost control.

Key Points

  • Shows the required cost efficiency for the remaining work to hit a chosen cost target.
  • Two variants: TCPI(BAC) = (BAC - EV) / (BAC - AC), and TCPI(EAC) = (BAC - EV) / (EAC - AC).
  • Compare TCPI to current CPI: TCPI > 1.0 means tougher-than-planned efficiency is needed; TCPI < 1.0 means the target is more attainable.
  • Use at project, control account, or work package level to focus interventions where they matter.
  • Drives decisions on cost containment, reforecasting (EAC/ETC), and whether to rebaseline.

Purpose of Analysis

  • Assess if the current cost target is realistic given actual performance to date.
  • Quantify how aggressively the team must perform to recover or maintain cost objectives.
  • Support decisions on corrective actions, funding requests, and stakeholder expectations.

Method Steps

  • Select the cost target: original BAC or a revised EAC if management has set a new goal.
  • Gather up-to-date EV and AC at the desired reporting level and period.
  • Calculate TCPI using the appropriate formula for the chosen target.
  • Compare TCPI to the current CPI and team capability to judge achievability.
  • Identify actions: reduce scope, increase productivity, adjust resources, negotiate rates, or revise the forecast.
  • Recommend a path: keep BAC, adopt a new EAC, or rebaseline; document rationale.
  • Monitor TCPI and CPI trends each cycle and update forecasts and reports.

Inputs Needed

  • BAC (Budget at Completion) for the relevant scope.
  • EV (Earned Value) to date for the same scope and time frame.
  • AC (Actual Cost) to date aligned with EV.
  • EAC (Estimate at Completion) if assessing against a revised target.
  • Current CPI (EV/AC) for context and comparison.
  • Approved changes, risk responses, and rate assumptions that affect remaining work.

Outputs Produced

  • Computed TCPI value against BAC and/or EAC.
  • Assessment of achievability versus current CPI and organizational constraints.
  • Recommended corrective or preventive actions and cost control measures.
  • Updated EAC/ETC and cost forecasts as needed.
  • Inputs to stakeholder reports, variance explanations, and management decisions.

Interpretation Tips

  • If TCPI(BAC) is much higher than CPI, meeting BAC is unlikely without significant changes.
  • If TCPI(EAC) is close to current CPI, the revised EAC is consistent with observed performance.
  • Values near 1.0 imply performance must match plan; higher than 1.1 indicates aggressive recovery is required.
  • If AC is at or above the target (BAC or EAC), the denominator approaches zero or turns negative, signaling the target is no longer attainable.
  • Use the same data cut and scope for EV and AC to avoid distorted ratios.

Example

Given BAC = 1,200,000; EV = 500,000; AC = 600,000.

  • TCPI(BAC) = (1,200,000 - 500,000) / (1,200,000 - 600,000) = 700,000 / 600,000 = 1.17.
  • Current CPI = EV / AC = 500,000 / 600,000 = 0.83.
  • Since 1.17 is far above 0.83, holding BAC is unlikely; consider revising EAC and implementing cost controls.
  • If a new EAC = 1,440,000 is adopted, TCPI(EAC) = (1,200,000 - 500,000) / (1,440,000 - 600,000) = 700,000 / 840,000 = 0.83, which aligns with current performance.

Pitfalls

  • Mixing BAC and EAC in the numerator or denominator and getting the wrong ratio.
  • Using stale EV/AC data or mismatched scope definitions between EV and AC.
  • Interpreting TCPI in isolation without comparing to CPI, resource capacity, and constraints.
  • Assuming TCPI > 1.0 is always achievable without considering schedule pressure and risk exposure.
  • Ignoring that a near-zero or negative denominator indicates the target is already unattainable.

PMP Example Question

A project has BAC = 1,200,000, EV = 600,000, and AC = 750,000. Management wants to meet the original BAC. What is the TCPI to achieve BAC?

  1. 0.80.
  2. 1.33.
  3. 0.75.
  4. 1.20.

Correct Answer: B — 1.33.

Explanation: TCPI(BAC) = (BAC - EV) / (BAC - AC) = (1,200,000 - 600,000) / (1,200,000 - 750,000) = 600,000 / 450,000 = 1.33. Values above 1.0 indicate the team must outperform the original plan on remaining work.

Agile Project Management & Scrum — With AI

Ship value sooner, cut busywork, and lead with confidence. Whether you’re new to Agile or scaling multiple teams, this course gives you a practical system to plan smarter, execute faster, and keep stakeholders aligned.

This isn’t theory—it’s a hands-on playbook for modern delivery. You’ll master Scrum roles, events, and artifacts; turn vision into a living roadmap; and use AI to refine backlogs, write clear user stories and acceptance criteria, forecast with velocity, and automate status updates and reports.

You’ll learn estimation, capacity and release planning, quality and risk management (including risk burndown), and Agile-friendly EVM—plus how to scale with Scrum of Scrums, LeSS, SAFe, and more. Downloadable templates and ready-to-use GPT prompts help you apply everything immediately.

Learn proven patterns from real projects and adopt workflows that reduce meetings, improve visibility, and boost throughput. Ready to level up your delivery and lead in the AI era? Enroll now and start building smarter sprints.

Explore the Course


Build the Sprint Reporting System, Not Another Prompt

AI Systems with Claude is our own course for Scrum Masters and Agile Project Managers, taught against one running project across eight teaching sections. You build five working systems and keep them: the sprint report machine, the retro intelligence system, the stakeholder comms engine, the backlog health monitor, and the risk and dependency tracker. Direct from HK School of Management and Technology, not on Udemy.

See What Is Included