Lessons learned
Lessons learned are documented insights from project experiences that explain what worked, what did not, and why. They are captured throughout the project to improve current performance and inform future projects.
Key Points
- Capture lessons continuously during the project, not only at closure.
- Record both positive practices to repeat and problems to avoid.
- Make each lesson actionable by including context, cause, and recommended actions.
- Use a structured format such as condition-action-result to keep lessons clear.
- Store items in a lessons learned register and update the organizational repository regularly.
- Share insights promptly with stakeholders and integrate them into plans, checklists, and processes.
Purpose of Analysis
- Improve project outcomes by translating experience into practical guidance.
- Prevent recurrence of issues and reinforce effective practices.
- Enable data-informed adjustments to current plans and processes.
- Build organizational knowledge that benefits future teams and projects.
Method Steps
- Plan the approach: define format, categories, roles, and timing for capturing lessons.
- Collect observations continuously through meetings, reviews, retrospectives, and day-to-day work.
- Analyze and group items, perform root cause analysis, and prioritize by impact and feasibility.
- Document each lesson using a clear template with context, cause, action taken or recommended, and outcome.
- Validate lessons with relevant stakeholders to ensure accuracy and buy-in.
- Apply lessons to the current project via updates to plans, checklists, and change requests as needed.
- Publish to the organizational repository and communicate to affected teams.
Inputs Needed
- Project management plan, baselines, and schedules.
- Performance data, dashboards, and metrics.
- Risk, issue, and change logs.
- Stakeholder feedback, surveys, and meeting minutes.
- Quality reports, test results, and audit findings.
- Retrospective outputs and action item reviews.
- Procurement and vendor performance records.
Outputs Produced
- Updated lessons learned register and entries in the organizational repository.
- Action items and process improvement proposals with owners and due dates.
- Updates to plans, procedures, templates, and checklists.
- Change requests when the lesson implies altering scope, process, or baselines.
- Training or coaching needs to reinforce new or improved practices.
Interpretation Tips
- Focus on root causes and system behavior, not individual blame.
- Assess whether the lesson is generalizable and note any prerequisites.
- Differentiate one-off events from patterns across iterations or phases.
- Keep entries concise, evidence-based, and linked to measurable outcomes.
- Assign an owner and follow-up date to ensure the lesson is acted upon.
Example
Mid-project, approvals were delaying work by several days. Analysis showed unclear decision rights and too many handoffs. The team documented a lesson: define decision makers early, streamline approval steps, and use a single intake channel. Actions taken included updating the stakeholder engagement plan, revising the workflow, and setting approval service levels. Cycle time for approvals improved by 25 percent in the next iteration.
Pitfalls
- Waiting until project close to gather lessons, causing loss of detail and missed opportunities to improve.
- Writing vague statements without context, cause, action, or measurable result.
- Capturing only failures or only successes, leading to a skewed knowledge base.
- Not sharing lessons or failing to integrate them into plans and organizational assets.
- Ignoring sensitivity and confidentiality when documenting incidents.
- Recording lessons without owners or follow-up, resulting in no real change.
PMP Example Question
During execution, the team discovers a new review technique that reduces defects. What should the project manager do next?
- Document it in the lessons learned register, share with the team, and apply it to current work as appropriate.
- Wait until project closing to document the lesson to avoid disrupting the schedule.
- Ask the PMO to mandate the technique across all projects immediately.
- Add the technique to the risk register for tracking and mitigation.
Correct Answer: A — Document it in the lessons learned register, share with the team, and apply it to current work as appropriate.
Explanation: Lessons should be captured as they occur and used to improve current performance. Organization-wide changes may follow after validation and proper governance.
HKSM