Burnup/burndown chart
A visual technique to track work progress over time. Burnup shows cumulative completed work versus total scope; burndown shows remaining work trending to zero. It supports fast status checks, forecasting, and visibility into scope changes.
Key Points
- Time is on the x-axis; work is on the y-axis, typically in story points, backlog items, or hours.
- Burnup has two lines: completed work and total scope; the vertical gap equals remaining work.
- Burndown shows remaining work approaching zero; often includes an ideal trend line for comparison.
- Updated frequently (daily in sprints) to enable timely course corrections.
- Useful at both sprint and release levels; supports adaptive and hybrid scheduling.
- Highlights schedule trends, blockers, and the impact of scope changes.
- Enables simple forecasting using recent velocity or throughput.
Purpose of Analysis
- Monitor schedule performance against a timebox or release plan.
- Forecast completion dates based on actual delivery rate.
- Expose scope growth or reduction clearly to stakeholders.
- Trigger timely discussions on capacity, risks, and impediments.
- Support data-driven decisions on scope, resources, and priorities.
Method Steps
- Choose the unit of work (story points, items, or ideal hours) and the time window (sprint or release).
- Establish the initial scope baseline and desired end date or timebox.
- Collect daily completions from the team and update cumulative totals.
- Plot burnup lines for completed work and total scope, or plot burndown for remaining work.
- Add an ideal trend line and annotate notable events such as scope changes or major blockers.
- Calculate simple forecasts using average velocity or rolling throughput.
- Review results with the team and stakeholders and agree on actions.
Inputs Needed
- Backlog with estimates in a consistent unit.
- Defined timebox length and calendar days for plotting.
- Baseline scope and any approved scope changes.
- Daily or periodic completion data from the team.
- Historical velocity or throughput for forecasting.
- Impediment and change logs for annotations.
Outputs Produced
- Updated burnup or burndown chart showing current status.
- Short-term and projected completion forecasts.
- Variance insights versus the ideal or planned trend.
- Visible record of scope changes and their timing.
- Recommended actions such as scope adjustment or capacity changes.
Interpretation Tips
- Burndown above the ideal line indicates behind plan; below indicates ahead.
- Flat sections suggest blockers or lack of completed work.
- Burnup scope line stepping up shows added scope; if completion rate is steady, expect a later finish.
- Diverging burnup lines mean growing gap to completion; converging lines signal progress toward done.
- Use a rolling average velocity to smooth volatility for forecasts.
- Annotate anomalies to prevent misinterpretation by stakeholders.
Example
A two-week sprint starts with 40 story points. The team completes 8, 7, and 5 points over the first three days, then adds a 5-point change on day 4.
- Burndown shows remaining work drop from 40 to 20 by day 3, then jump to 25 on day 4 due to scope increase.
- Burnup shows completed rising to 20 by day 3 while the scope line steps from 40 to 45 on day 4, keeping the gap visible.
- Using a velocity of about 7 points per day, the forecast suggests finishing near the end of the timebox if impediments are removed.
Pitfalls
- Mixing units of measure mid-sprint, making the trend unreliable.
- Updating infrequently, which hides emerging schedule issues.
- Ignoring scope changes on a burndown, leading to misleading “behind plan” signals.
- Over-relying on straight-line projections despite changing capacity or holidays.
- Counting started work as completed, which inflates progress.
- Not annotating major events, causing stakeholders to misread the chart.
PMP Example Question
A Scrum team’s burndown is trending above the ideal line, and mid-sprint the Product Owner adds two user stories. What should the project manager use to clearly show the impact of the added scope while maintaining transparent schedule monitoring?
- Switch to a cumulative flow diagram to show work-in-progress states.
- Use a burnup chart that displays both completed work and total scope lines.
- Rebaseline the burndown so it matches the new target and hides variance.
- Extend the sprint length to restore the burndown to the ideal line.
Correct Answer: B — Use a burnup chart that displays both completed work and total scope lines.
Explanation: Burnup charts explicitly show scope additions on the scope line while tracking completed work. This keeps schedule performance transparent without masking variance or changing the timebox.