Release Planning Schedule

A Release Planning Schedule is a primary output of the Conduct Release Planning process. It identifies which deliverables will be provided to customers and specifies the planned cadence and target dates for each release. Not every Sprint must end with a customer release.

Key Points

  • Produced during Conduct Release Planning to map deliverables to customer releases.
  • Defines the release cadence and target dates or windows for each drop.
  • Provides guidance for teams and stakeholders and is updated as priorities or capacity change.
  • Allows for Sprints without a customer-facing release when appropriate.

Example

On a mobile app program, the team plans customer releases after Sprints 3, 6, and 9. The Release Planning Schedule lists features for Release 1 on Mar 15 (login and password reset), Release 2 on Apr 26 (biometric authentication and session timeout), and Release 3 on Jun 7 (in-app notifications). Sprints 4 and 8 focus on internal refactoring and performance work without a public release.

PMP Example Question

Which artifact shows which deliverables will be shipped to customers and when, while acknowledging that not every Sprint ends with a release?

  1. Release Planning Schedule
  2. Sprint Backlog
  3. Definition of Done
  4. Sprint Burndown Chart

Correct Answer: A — Release Planning Schedule

Explanation: The Release Planning Schedule outlines which deliverables go to customers and the planned cadence and dates for releases. Other artifacts do not define release timing to customers.

Advanced Project Management — Measuring Project Performance

Move beyond guesswork and status reporting. This course helps you measure real progress, spot problems early, and make confident decisions using proven project performance techniques. If you manage complex projects and want clearer visibility and control, this course is built for you.

This is not abstract theory. You’ll work step by step through Earned Value Management (EVM), learning how cost, schedule, and scope come together to show true performance. You’ll build a solid foundation in EVM concepts, understand why formulas work, and learn how performance data actually supports leadership decisions.

You’ll master Work Breakdown Structures (WBS), control accounts, and budget baselines, then apply core EVM metrics like EAC, TCPI, and variance analysis. Through a detailed real-world example, you’ll forecast outcomes, analyze trends, and understand contingencies and management reserves with confidence.

Learn how experienced project managers monitor performance, communicate results clearly, and take corrective action before projects slip. With practical exercises and hands-on analysis, you’ll be ready to apply EVM immediately. Enroll now and start managing performance with clarity and control.

Explore the Course


Build an ICS/OT cybersecurity foundation that fits the real environment

Standard IT controls can disrupt the industrial systems they are meant to protect. Learn how to assess OT risk, design zones and conduits, apply IEC 62443 security levels, use MITRE ATT&CK for ICS, and establish passive asset visibility without risking production. Eight reconstructed incidents connect attacker techniques to the controls that failed, giving you the vocabulary and judgment to make credible security decisions from day one.

Explore the Course