Issues

Issues are confirmed, present problems or conditions affecting the project now; unlike risks, they do not require probability analysis and instead need ownership, tracking, and resolution.

Key Points

  • Issues are happening now and have certain impact on the project.
  • They are recorded in an issue log with an owner, priority, due date, and status.
  • They require immediate attention, escalation as needed, and a clear action plan.
  • They are different from risks (uncertain future events) and may lead to change requests or follow-up risks.

Example

A vendor misses a critical hardware delivery, blocking system testing. The project manager logs it as an issue, assigns the procurement lead as owner, sets a due date to secure an alternate supplier, escalates to the steering committee, and updates the schedule once a workaround is confirmed.

PMP Example Question

During Sprint 4, the payment gateway stops working in the test environment, halting integration testing. How should the project manager classify and handle this situation?

  1. As a risk; perform probability and impact analysis and update the risk register.
  2. As an issue; record it in the issue log, assign an owner and due date, and initiate resolution actions.
  3. As a change request; skip logging and move directly to the change control process.
  4. As an assumption; document it and continue with planned work.

Correct Answer: B — Issue

Explanation: The problem is already occurring and affecting work, so it is an issue that needs ownership, tracking, and immediate resolution, not a probability assessment.

Project Management with AI: From Initiation to Closing

Build a practical project management process from initiation to closing with our Project Management: From Initiation to Closing with AI course. Learn how to move from informal project coordination to a structured, repeatable approach using PMBOK-aligned workflows, real examples, and professional templates.

This hands-on course follows a complete project lifecycle. You will learn how to write a project charter, define scope, build a work breakdown structure, develop a schedule, estimate costs, manage risks, engage stakeholders, execute the work, monitor performance, and close the project properly.

You will also learn how to use AI tools to accelerate project management work. The course includes reusable prompts, downloadable templates, assignments, and worked examples that show how project documents connect from one stage to the next.

The course is designed for professionals, team leads, coordinators, analysts, and new project managers who need practical skills they can apply at work. Enroll now and build the confidence to manage projects with structure, clarity, and control.



Stop Managing Admin. Start Leading the Future!

HK School of Management helps you master AI-Prompt Engineering to automate chaos and drive strategic value. Move beyond status reports and risk logs by turning AI into your most capable assistant. Learn the core elements of prompt engineering to save hours every week and focus on high-value leadership. For the price of lunch, you get practical frameworks to future-proof your career and solve the blank page problem immediately. Backed by a 30-day money-back guarantee-zero risk, real impact.

Enroll Now