Issues

Issues are confirmed, present problems or conditions affecting the project now; unlike risks, they do not require probability analysis and instead need ownership, tracking, and resolution.

Key Points

  • Issues are happening now and have certain impact on the project.
  • They are recorded in an issue log with an owner, priority, due date, and status.
  • They require immediate attention, escalation as needed, and a clear action plan.
  • They are different from risks (uncertain future events) and may lead to change requests or follow-up risks.

Example

A vendor misses a critical hardware delivery, blocking system testing. The project manager logs it as an issue, assigns the procurement lead as owner, sets a due date to secure an alternate supplier, escalates to the steering committee, and updates the schedule once a workaround is confirmed.

PMP Example Question

During Sprint 4, the payment gateway stops working in the test environment, halting integration testing. How should the project manager classify and handle this situation?

  1. As a risk; perform probability and impact analysis and update the risk register.
  2. As an issue; record it in the issue log, assign an owner and due date, and initiate resolution actions.
  3. As a change request; skip logging and move directly to the change control process.
  4. As an assumption; document it and continue with planned work.

Correct Answer: B — Issue

Explanation: The problem is already occurring and affecting work, so it is an issue that needs ownership, tracking, and immediate resolution, not a probability assessment.

Agile Project Management & Scrum — With AI

Ship value sooner, cut busywork, and lead with confidence. Whether you’re new to Agile or scaling multiple teams, this course gives you a practical system to plan smarter, execute faster, and keep stakeholders aligned.

This isn’t theory—it’s a hands-on playbook for modern delivery. You’ll master Scrum roles, events, and artifacts; turn vision into a living roadmap; and use AI to refine backlogs, write clear user stories and acceptance criteria, forecast with velocity, and automate status updates and reports.

You’ll learn estimation, capacity and release planning, quality and risk management (including risk burndown), and Agile-friendly EVM—plus how to scale with Scrum of Scrums, LeSS, SAFe, and more. Downloadable templates and ready-to-use GPT prompts help you apply everything immediately.

Learn proven patterns from real projects and adopt workflows that reduce meetings, improve visibility, and boost throughput. Ready to level up your delivery and lead in the AI era? Enroll now and start building smarter sprints.

Explore the Course


Build complete project plans in minutes with AI

Learn how to use AI to create charters, WBSs, schedules, risk registers, and executive reports while staying in control. This course gives you prompt templates and practical workflows based on real project work. Practical skills, tools, and guidance you can apply right away. Covered by Udemy's 30-day refund policy.

Learn More