Internal dependencies

Links among tasks, products, or activities that the Scrum Team directly manages and that fall within the team's own scope of work.

Key Points

  • Owned and controlled by the Scrum Team, not by outside parties.
  • Handled through backlog refinement, Sprint Planning, and Daily Scrum to align sequencing.
  • Made visible on the team's board to manage order, handoffs, and timing.
  • Can often be reduced by slicing work, decoupling, or redefining acceptance criteria.

Example

The team's story "Build checkout UI" must wait for the same team's story "Finalize payment API endpoints." Both items are in the Scrum Team's backlog, so the team sequences them within the Sprint to avoid blocking.

PMP Example Question

A Scrum Team cannot start creating the reporting dashboard until their own data engineer completes the data model in the same Sprint. What type of dependency is this?

  1. External dependency
  2. Internal dependency
  3. Mandatory dependency only
  4. Regulatory dependency

Correct Answer: B — Internal dependency

Explanation: The work and control reside within the same Scrum Team and within their scope, so it is an internal dependency.

Agile Project Management & Scrum — With AI

Ship value sooner, cut busywork, and lead with confidence. Whether you’re new to Agile or scaling multiple teams, this course gives you a practical system to plan smarter, execute faster, and keep stakeholders aligned.

This isn’t theory—it’s a hands-on playbook for modern delivery. You’ll master Scrum roles, events, and artifacts; turn vision into a living roadmap; and use AI to refine backlogs, write clear user stories and acceptance criteria, forecast with velocity, and automate status updates and reports.

You’ll learn estimation, capacity and release planning, quality and risk management (including risk burndown), and Agile-friendly EVM—plus how to scale with Scrum of Scrums, LeSS, SAFe, and more. Downloadable templates and ready-to-use GPT prompts help you apply everything immediately.

Learn proven patterns from real projects and adopt workflows that reduce meetings, improve visibility, and boost throughput. Ready to level up your delivery and lead in the AI era? Enroll now and start building smarter sprints.



Lead with clarity, influence, and outcomes.

HK School of Management brings you a practical, no-fluff Leadership for Project Managers course—built for real projects, tight deadlines, and cross-functional teams. Learn to set direction, align stakeholders, and drive commitment without relying on title. For the price of a lunch, get proven playbooks, and downloadable templates. Backed by a 30-day money-back guarantee—zero risk, high impact.

Learn More