External Dependencies

Work that the Scrum Team relies on but that is owned, performed, or delivered by people or systems outside the team. These outside tasks, services, or deliverables are required to complete the team’s work, yet they are typically beyond the team’s direct control.

Key Points

  • Arise when progress depends on vendors, other internal teams, regulators, or third-party systems.
  • Cannot be fully planned or changed by the Scrum Team alone; require coordination, agreements, and lead time.
  • Should be identified early, made visible on boards/backlogs, and tracked with clear owners, dates, and risk status.
  • Mitigation includes SLAs, integration plans, buffers, fallback options, and frequent communication with external parties.

Example

A Scrum Team building a payment feature must integrate with a bank’s API. The bank needs two weeks to enable a sandbox account. The team marks this as an external dependency, coordinates dates with the bank, plans other work in the interim, and tracks the dependency and risk.

PMP Example Question

During Sprint Planning, the team learns a feature depends on a third-party API update that will be delivered next month. What should the Scrum Team do first?

  1. Add the third-party work to the Sprint and commit to finishing it now.
  2. Record it as an external dependency, coordinate dates with the external owner, plan unblocked work, and track the risk.
  3. Add more developers to remove the dependency.
  4. Cancel the Sprint until the API is ready.

Correct Answer: B — Manage the external dependency through coordination and plan around it

Explanation: The work is outside the team’s control, so the team should make the dependency visible, coordinate with the external party, adjust plans to avoid blockage, and monitor the risk.

AI for Agile Project Managers and Scrum Masters

Become an AI-first leader and transform your agile practice by leveraging artificial intelligence as your most powerful co-pilot. This course is designed to help you drive efficiency, insight, and innovation, ensuring you stay at the forefront of a rapidly evolving project management landscape.

This isn't about replacing human intuition—it's about augmenting it. You'll master prompt engineering to automate mundane tasks, freeing up your time for high-impact strategic leadership and creative problem-solving. Learn to refine backlogs, create strategic roadmaps, and integrate AI seamlessly into your agile ceremonies.

Gain predictive power by using AI-driven insights to anticipate project risks and seize new opportunities for more reliable outcomes. We deliver practical, prompt-based workflows and proven strategies built around real-world agile challenges that you can implement immediately within your framework.

Master foundational AI concepts specifically relevant to Scrum environments while developing advanced skills to handle diverse agile scenarios. You will learn to champion an AI-enabled culture within your organization, fostering a dynamic environment of continuous improvement and superior team delivery.

Learn alongside professionals around the world working in project leadership and delivery.

Explore the Course


Build the Sprint Reporting System, Not Another Prompt

AI Systems with Claude is our own course for Scrum Masters and Agile Project Managers, taught against one running project across eight teaching sections. You build five working systems and keep them: the sprint report machine, the retro intelligence system, the stakeholder comms engine, the backlog health monitor, and the risk and dependency tracker. Direct from HK School of Management and Technology, not on Udemy.

See What Is Included