Change Request(s)

A change request is the usual mechanism for proposing a modification to the project or product. It remains pending and has no effect until it is formally reviewed and approved.

Key Points

  • Used to propose changes to scope, schedule, cost, quality, requirements, deliverables, or project documents.
  • Should be documented with justification and impact analysis, then routed through the agreed change control process (e.g., CCB or product governance).
  • Status is tracked (submitted, under review, approved, rejected, deferred); only approved requests are implemented and baselines updated.
  • In agile environments, approved changes often become prioritized backlog items; governance still applies before altering commitments or baselines.

Example

A stakeholder asks mid-project to add a new compliance report. The project manager logs a change request, the team estimates schedule and cost impact, and the CCB reviews it. After approval, the plan and baselines are updated and the work is scheduled for the next iteration; if rejected, no change is made.

PMP Example Question

Which statement best describes a change request?

  1. It is implemented immediately to avoid delays.
  2. It is a formal proposal that must be reviewed and approved before any change is made.
  3. It is used only when defects are found during testing.
  4. It is optional documentation for minor scope adjustments.

Correct Answer: B — A formal proposal requiring approval before implementation

Explanation: Change requests are formal proposals and have no effect until approved; they are not immediate, not limited to defects, and are not optional for minor changes unless governance explicitly allows it.

Leadership for Project Managers Course

Lead with clarity, confidence, and real impact. This Leadership for Project Managers course turns day-to-day challenges—unclear priorities, tough stakeholders, and cross-functional friction—into opportunities to guide teams and deliver outcomes that matter.

You’ll learn practical leadership skills tailored to project realities: setting direction without overcontrol, creating alignment across functions, and building commitment even when authority is limited. We go beyond theory with tools you can use immediately—one-sentence visioning, stakeholder influence maps, decision framing, and feedback scripts that actually land.

Expect hands-on frameworks, real-world examples, and guided practice to prepare for tough moments—executive readouts, resistance from stakeholders, and high-stakes negotiations. Downloadable templates and checklists keep everything actionable when the pace gets intense.

Ready to influence without waiting for a bigger title? Join a community of ambitious PMs, sharpen your edge, and deliver with purpose—project after project.



Launch your Agile career!

HK School of Management helps you master Agile and Scrum—faster. Learn practical playbooks, AI-powered prompts, and real-world workflows to plan smarter, deliver sooner, and keep stakeholders aligned. For the price of lunch, you’ll get templates, tools, and step-by-step guidance to level up your projects. Backed by our 30-day money-back guarantee—zero risk, clear path to results.

Learn More