Chapter 18: Earned Value Management Questions
A Comprehensive Guide to Real-World Success
How do you calculate and interpret Cost Variance (CV) and Schedule Variance (SV) in Earned Value Management?
Cost Variance (CV) is calculated as Earned Value (EV) minus Actual Cost (AC). A positive CV indicates the project is under budget, while a negative CV suggests it's over budget. Schedule Variance (SV) is calculated as EV minus Planned Value (PV). A positive SV shows the project is ahead of schedule, and a negative SV means it’s behind schedule.
What is the difference between Cost Performance Index (CPI) and Schedule Performance Index (SPI), and how do you use them to assess project health?
The Cost Performance Index (CPI) is the ratio of EV to AC and reflects cost efficiency—values above 1 indicate the project is under budget, while values below 1 suggest it’s over budget. The Schedule Performance Index (SPI) is the ratio of EV to PV, showing schedule efficiency. An SPI greater than 1 indicates the project is ahead of schedule, while less than 1 means it’s behind.
Can you explain the significance of the Estimate at Completion (EAC) metric and describe how you calculate it using EVM?
Estimate at Completion (EAC) predicts the total cost of a project at completion, based on current performance. It is important for forecasting future budget requirements and ensuring the project stays within financial constraints. One common way to calculate EAC is by using the formula: EAC = Budget at Completion (BAC) divided by Cost Performance Index (CPI).
How would you address a situation where EVM metrics indicate a project is significantly over budget and behind schedule?
If EVM metrics show a project is over budget and behind schedule, corrective actions may include revising the project plan, reallocating resources, adjusting the scope, or modifying timelines. It’s crucial to identify root causes and implement strategies to optimize performance and bring the project back on track.
Describe a time when you used EVM to make a critical decision on a project. What was the outcome?
In a past project, EVM revealed significant cost overruns early in the process. Using this insight, I made the decision to reallocate resources and reprioritize tasks. This corrective action helped address the cost issues, and the project was completed on time and within budget, avoiding further delays and financial impact.
If the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.90, how is the project performing and why?
The project is over budget (CPI < 1) and behind schedule (SPI < 1). This indicates that the project is spending more than planned for the work completed and is progressing slower than expected.
A project has a CPI of 1.10 and an SPI of 0.95. What does this mean about the project's performance?
The project is under budget (CPI > 1) but slightly behind schedule (SPI < 1). This suggests cost efficiency but slower-than-planned progress.
Your project reports a CPI of 1.00 and an SPI of 1.20. How is the project doing, and what might this indicate about resource usage and schedule progress?
The project is on budget (CPI = 1) and ahead of schedule (SPI > 1). This indicates that the work is progressing faster than planned without exceeding the budget.
Close your knowledge gap
Understanding Earned Value Management (EVM), along with project finances and accounting, is crucial. If you’re unable to discuss these concepts confidently in an interview, it’s important to address this knowledge gap. You need to have a solid grasp of project accounting principles, as EVM is just one tool in a larger framework. If you recognize this as a weakness, I highly recommend taking the time to improve your understanding.
Visit our website blog and reed free articles on EVM that you can use to enhance your knowledge. Additionally, we offer a comprehensive advanced project management course. If those options don’t work for you, consider exploring project accounting or advanced project management courses at a college or university you prefer.
Advanced Project Management — Measuring Project Performance
Move beyond guesswork and status reporting. This course helps you measure real progress, spot problems early, and make confident decisions using proven project performance techniques. If you manage complex projects and want clearer visibility and control, this course is built for you.
This is not abstract theory. You’ll work step by step through Earned Value Management (EVM), learning how cost, schedule, and scope come together to show true performance. You’ll build a solid foundation in EVM concepts, understand why formulas work, and learn how performance data actually supports leadership decisions.
You’ll master Work Breakdown Structures (WBS), control accounts, and budget baselines, then apply core EVM metrics like EAC, TCPI, and variance analysis. Through a detailed real-world example, you’ll forecast outcomes, analyze trends, and understand contingencies and management reserves with confidence.
Learn how experienced project managers monitor performance, communicate results clearly, and take corrective action before projects slip. With practical exercises and hands-on analysis, you’ll be ready to apply EVM immediately. Enroll now and start managing performance with clarity and control.
Lead with clarity, influence, and outcomes.
HK School of Management brings you a practical, no-fluff Leadership for Project Managers course—built for real projects, tight deadlines, and cross-functional teams. Learn to set direction, align stakeholders, and drive commitment without relying on title. For the price of a lunch, get proven playbooks, and downloadable templates. Backed by a 30-day money-back guarantee—zero risk, high impact.
Learn More
HKSM